Project Name: Construction works of internal road asphalt overlay works of Bishoftu Automotive Industry.
Project Client and Consultant: FDRE Metals and Engineering Corporation (METEC) and Defense Construction Design Enterprise respectively.
Contractor: ASER Construction PLC
Project Description
The project scope includes construction of concrete asphalt overlay works for nearly 4km length with 7m width with minor base course works.
Project Location: Debrezeit, Oromia
Current Project Status: As of December 12, 2016 construction of asphalt overlay for more than 2.5 Km has been completed and the total work is expected to be completed on December 15, 2016.
Machinery Mobilization and Work Force: A total of 5 machineries are deployed and 35 work forces are engaged on the project work.