ASER to Complete Kilinto & Koye-Fiche Area Water Supply Project admin February 18, 2017

ASER to Complete Kilinto & Koye-Fiche Area Water Supply Project

Project Name: Supply and Installation of Pipes and Fittings and Construction of Civil works of Kilinto and Koye-Fiche area Water Supply

Project Description: Supply and install pipes and fittings including civil work construction from well field to koye reservoir.

Client and Consultant: Client of the project is Addis Ababa & Sewerage Authority Water & Sanitation Development and Rehabilitation Project Office. Oromia Water Works Design and Supervision Enterprise (OWWDSE) is the consulting firm.

Commencement Date: ASER Construction Plc. took over the project site and commenced operation in early June 2015.

Project Location: Akaki Kality, Addis Ababa

Current Project Progress: As of February, 2017 the physical status of the project has been reached 93 percent as construction for both service reservoirs of 10000m3 and 2500 m3 has been reached 99 percent and overall the project work will be completed within the next few months.

Project Work Force: The project currently provides job opportunity for 25 permanent and 136 temporary workers.

Machinery Mobilization: A total of 19 heavy and small machinery’s are currently deployed for the project.